Constellation exec says grid operator told company Three Mile Island can’t connect until 2031

INVESTING.COMMar 26, 7:36 PM UTC

Key insights

  • Constellation Energy shares fell 3% after PJM indicated that the restarted Three Mile Island plant (Crane Clean Energy Center) may not connect to the grid until 2031, four years later than anticipated. This delay impacts Constellation's contract to supply power to Microsoft data centers and highlights potential infrastructure bottlenecks for meeting rising electricity demand from tech and electrification.
Constellation exec says grid operator told company Three Mile Island can’t connect until 2031

By Laila Kearney

NEW YORK, March 26 (Reuters) - U.S. grid operator PJM has told Constellation Energy that the former Three Mile Island nuclear power plant in Pennsylvania likely will not be able to connect to the grid until 2031, four years later than planned, the company said at the CERAWeek energy conference in Houston on Thursday.

Constellation is working to resume operations at the nuclear power plant, which is being renamed the Crane Clean Energy Center, to supply electricity to Microsoft data centers.

The company will be ready to produce electricity from the plant by its earlier goal, and it is speaking with grid operator PJM Interconnection to reduce the timeline, said David Dardis, chief external affairs and growth officer at Constellation.

“We will have it ready to go in 2027," Dardis told Reuters.

PJM, in its initial feedback on the interconnection plan for the restarted plant, said it would take until 2031 to complete some of the transmission upgrades needed for the plant to connect to the grid. Constellation is in discussions with transmission owners to accelerate the timeline, Dardis said.

Shares of the company were down 3% following Reuters’ report.

Constellation, the country’s biggest independent power producer, announced in 2024 that it had contracted with Microsoft to reopen the nuclear power plant. No fully shut nuclear power plant has ever been restarted, but as demand rises from Big Tech data centers and the electrification of buildings and transportation, three U.S. plants are currently in that process.